Control Tab

To set Power Flow options, from the Power Flow menu, select PF Options.

Select the Control tab to specify the behavior of a power flow study.

Figure 1: Control Tab of Power Flow Options Dialog Box

Option Description

Solution Mismatch

Solution mismatch controls the tolerance of power flow convergence and how long convergence will take. The smaller the mismatch, the more difficult it becomes to make power flows and voltages converge to a solution.

MW

Convergence tolerance of the bus megawatts. Flows into a bus converging to within this tolerance of the actual load on the bus is considered to be an acceptable solution. The default setting of 0.0001 MW (100 watts) is an extremely accurate tolerance.

MVAR

Convergence tolerance of the bus megavars. Flows into a bus converging to within this tolerance of the actual load on the bus is considered to be an acceptable solution. The default setting of 0.0001 MVAR (100 vars) is an extremely accurate tolerance.

kV PU

This field determines the bus voltage tolerance for generator PQG buses that switch back to PV buses. Bus voltage must converge to within this tolerance of the actual load on the bus to be an acceptable solution.

Iterations

Number of solution iterations allowed for convergence. For most typical industrial systems, only five to six iterations are required for convergence. If many load tap changers or tighter controls are used, 10-15 iterations may be required.

Isolated Subsystems

All power flow solutions require a swing (slack) source to account for system losses, etc. (see Swing Sources). To solve an isolated system requires you or the program to add a swing source. An isolated subsystem is when a portion of the one-line is separated from the main part and does not have its own swing source (see below). This typically occurs when you open a feeder breaker on a radial line or transformer. It may also occur when opening multiple breakers on more complicated looped systems.

  • Don't Allow: When you perform a solve and an isolated subsystem is detected by EasyPower, you receive a message and the solve will not be performed.
  • Ignore: When you perform a solve and an isolated subsystem is detected by EasyPower, the regular solution and output will occur but no output will be displayed for the isolated subsystem.
Tap Acceleration Factor

Factor used to slow speed through iterations by changing LTC of transformer when changing taps.

Motor Start Solution Method

The motor start solution method controls the algorithm used and the way loads are modeled when motors are started in the power flow analysis.

Constant Impedance, Non-iterative

A direct solution method using the admittance matrix and voltages from the existing power flow solution. All constant kVA and current loads are converted to constant impedance loads for this method. Starting motors are also modeled as a constant impedance. The advantages of this method are its speed since the solution is direct (no iterations are required), and the fact that it cannot diverge. The disadvantage is that it may be non-conservative depending on the solution voltages. The reason for this is that constant impedance loads are a function of the square of the voltage. As the system voltage is reduced, the load is proportionally reduced also, effectively reducing the load.

Constant kVA, Iterative

An iterative method using the same algorithm as the power flow solution. All constant kVA, current, and impedance loads remain modeled as they are in a standard power flow solution. Starting motors are modeled as a constant impedance. The advantage of this method is its accuracy since it correctly models all load types. The disadvantage is that it can diverge (fail to solve) if the voltages become too low, or the loads are too high.

Output Criteria
Area

Enables you to specify a specific bus area that will be reported in text results.

Zone

Enables you to specify a specific bus zone that will be reported in text results.

Overload Threshold

Sets the limit for flagging overload violations. Equipment items not in violation, yet within this threshold %, are highlighted for easy identification. This setting applies to both one-line output and text result output.

For example, suppose a cable rated for 500A is loaded to 480A, and the Overload Threshold is set to -10 percent. The percent overload is determined as follows.

  • Overload threshold in amperes = 500A x (1 ‑ .10) = 450A
  • Overload % = (480 ‑ 500)/500 = ‑4%

Note that the overload is negative, indicating that while the cable is not overloaded, it is 6 percent over the threshold limit of 10 percent. Therefore, it will be highlighted on the one-line when you click Overloads.

You can also display the overload as a percentage of the equipment rating. To use this option, in the Database Edit focus, select Tools > Options, click System and select the Use 100% convention for displaying analysis overloads/overduties check box.

Bus Undervoltage / Overvoltage Threshold

Sets the minimum and maximum limit for determining voltage violations. Bus voltages that either exceed the maximum limit or drop below the lower limit are in violation. Buses in violation are highlighted on the one-line and printed in voltage violation text reports.

More Information

Power Flow Analysis  
Controlling the Analysis  
Power Flow Options  
     

www.easypower.com

EasyPower, LLC

7730 SW Mohawk St.

Tualatin, OR 97062

(503)655-5059

techsupport@easypower.com

feedback@easypower.com

EasyPower knowledge base

EasyPower Version 9.8

Copyright © 2017 EasyPower, LLC. All Rights Reserved.

Help was last updated on 7/10/2017