Control Tab (IEC)
To set short circuit options, from the Short Circuit focus, click SC Options.
Select the Control tab to specify various parameters for controlling the behavior of a short circuit study.
Figure 1: Control Tab of Short Circuit Options Dialog Box
Option | Description | ||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Fault Type for 3PH buses |
For 3-phase faults, there are four different types of faults available during a short circuit analysis. The default is 3 Phase which is generally used to determine the highest available currents for equipment duty comparisons, and relaying. The other types, Line to Ground, Double Line to Ground, and Line to Line are generally used for specialized relaying applications or system troubleshooting. You can specify the phases to fault for each fault type. During short circuit analysis, the program automatically changes the display phases if the phases selected appear on the one-line do not match these fault values. Note: Your phase descriptions may be different than described here if they have been customized in Tools > Options > Terminology. |
||||||||||||
Fault Type for 1PH buses |
For single-phase faults, there are three different types of faults available during a short circuit analysis. You can specify the phases to fault for each fault type. The options are as follows:
|
||||||||||||
"Fault All" Filters | Enables you to specify a specific bus Area, Zone, and kV Range that to fault and report when you fault multiple or all buses. | ||||||||||||
Include Single Phase Buses |
Selects whether single-phase buses are included when bus faults are performed. By default, this option is selected. |
||||||||||||
Equipment Duty Threshold |
Sets the lower limit for flagging breaker violations in SmartDuty™. If the threshold is set to -10 percent, SmartDuty™ flags all equipment which has short circuit duties within 10 percent of their maximum rating (greater than 90% of their rating). Note: The ability to automatically check equipment duties during analysis is only available if you have purchased the SmartDuty™ option to EasyPower. Note: You must click Equipment Duty from the Short Circuit focus for this field to have any effect on the one-line result output. For more information on IEC equipment duty calculations, see IEC Equipment Duty Calculations. |
||||||||||||
Compare 1PH Device Rating to Device/Bus Current |
For more information, see Equipment Duty for Single-Phase Devices. |
||||||||||||
You can set a threshold for remote bus voltages. Buses that violate this threshold are highlighted. You can control the highlighting for high voltage and low voltage buses using Short Circuit Options > One-line Output > Voltage Sensitivity Highlighting. This is applicable only for single bus faults. |
|||||||||||||
DC short circuit calculations use this voltage per unit. |
|||||||||||||
This is the voltage correction factor (commonly referred to as C Factor). The C Factor is used for modifying equipment impedances and the driving point voltage. IEC recommends calculations for minimum and maximum short circuit currents. Selecting C Factor for Max or Min enables the desired type of calculation. You can perform calculations for only one of the two at any time. The C Factors differ by voltage levels. The default values in the Options dialog box are those recommended by IEC-60909, and are summarized below. You can change these values if needed. |
|||||||||||||
Voltage Range |
|
||||||||||||
One of the four breaking currents (0.02s, 0.05s, 0.1s, 0.25s) can be chosen as a global default for TCC clipping and tick marks in LV breakers and fuses. You can change the individual settings of the breakers and fuses in their respective dialog boxes. |
|||||||||||||
Peak currents are calculated based on method B or method C as described in IEC 60909. Worst case uses the higher current after comparing method B and C. | |||||||||||||
Select this option to ensure unbalanced faults such as single-line-to-ground, line-to-ground, and double-line-to-ground use the X/R ratio of the 3 phase fault to calculate the peak current in method C. If this option is not selected, the X/R of the unbalanced fault is used for peak current calculations. |